techhardy

Variant 01-A

Off-grid / Backup (Philippines)

Battery-based system with no grid connection: panels, battery, MPPT charge controller, inverter, wiring and protection, with costs in pesos.

Not yet Reviewed

System24 V · 900 W of panels · 200 Ah battery
Voltage your system runs on
W

About 2,760 Wh a day.

Start-up surge: 100 W. Required: enter the inverter's surge rating in 05 Inverter.

  1. Solar panels
  2. MPPT charge controller
  3. Busbar (+ and −)
  4. Battery
  5. Inverter
  6. Your devices

Panel frames, metal cases and both surge protectors connect to a ground rod.

Legend

  • Solar panels
  • Charge controller (DC to DC)
  • Busbar
  • Battery
  • Inverter (DC to AC)
  • Your devices
  • Fuse
  • Circuit breaker
  • Disconnect switch
  • Surge protector to ground
  • Ground (earth)

Standard electrical symbols (IEC 60617).

Parts at a glance

PartAmountRating
9100 W each · 900 W total
3at least 9.3 A · buy 10 A · ≥ 74.3 V DC
1≥ 74.3 V DC
1at least 27.7 A · buy 32 A · ≥ 74.3 V DC
20 m10 mm² (≈ 8 AWG)
150 A, 24 V battery
1at least 62.5 A · buy 63 A · ≥ 30 V DC
3 m22 mm² (≈ 4 AWG)
1 pair≥ 70 A
1at least 62.5 A · buy 70 A · ≥ 30 V DC
1≥ 70 A · ≥ 30 V DC
1 pair≥ 70 A
124 V · 200 Ah
1at least 19.9 A · buy 20 A · ≥ 30 V DC
3 m3.5 mm² (≈ 12 AWG)
1300 W · surge ≥ 100 W needed
1at least 1.7 A · buy 10 A · 30 mA
1 set2 mm² (≈ 14 AWG)
12-pole, ≥ your house main breaker
1230 V
16 m14 mm² (≈ 6 AWG)
1—

Checks

0 to fix5 to check13 OK
  • Check thisBuy a battery whose maximum continuous discharge current (BMS limit) is at least 16 A: the inverter's draw when the battery is nearly empty.05 Inverter
  • Check thisRequired: enter the inverter's surge (peak) rating from its label. Needed: at least 100 W for a few seconds (everything running at once).05 Inverter
  • Check thisCheck the controller's manual for the largest wire its terminals take. This design uses 22 mm² (≈ 4 AWG), too thick for many controllers.04 Charge controller
  • Check thisEnter the main Class T fuse's DC breaking capacity (kA, on its label) and the battery's short-circuit current (datasheet or seller) to check it can stop a battery short.07 Fuses, breakers & grounding
  • Check thisAsk your electrician whether your local code also needs: ground-fault protection for the panels (NEC 690.5), and a quick-shutdown switch for panels on a roof (NEC 690.12). Many charge controllers and inverters include ground-fault protection; check the manual.07 Fuses, breakers & grounding
  • 13 checks passed
    • Battery: 3,840 Wh usable, 3,174 Wh needed.
    • Panels: 3,240 Wh a day, 3,174 Wh needed.
    • Charging at up to 50 A, within what a typical 200 Ah lithium battery accepts (about 100 A). Enter the battery's maximum charge current to check it exactly.
    • Controller 50 A: 46.9 A needed.
    • Panels on a cold morning: about 74.3 V, under the controller's 150 V limit.
    • Fit each panel row with its own 10 A fuse in a combiner box: a faulty row could get 14.8 A, more than the panel's 10 A rating.
    • Panels on a hot day: about 47.7 V, enough to charge (32.0 V needed, rule of thumb).
    • Inverter 300 W: 150 W needed.
    • Panels → controller wire: 10 mm², loses 1.26%, safe up to 41 A.
    • Controller → battery wire: 22 mm², loses 0.46%, safe up to 79 A.
    • Battery → inverter wire: 3.5 mm², loses 1.40%, safe up to 20 A.
    • Main Class T fuse: 70 A covers the 62.5 A in or out of the battery.
    • Panels stay under 80 V (up to 74.3 V): no arc-fault protection needed (NEC 690.11).

These numbers are estimates. Check them against your own measurements and product labels before you build. Performance depends on weather, temperature, equipment and installation. Have a licensed electrician check the design. Follow the Philippine Electrical Code.